Projek Penswastaan Lebuhraya Bertingkat Sungai Besi (SUKE)

HOME  >  PROJECTS

Projek Penswastaan Lebuhraya Bertingkat Sungai Besi – Ulu Kelang (SUKE) Pakej CB1: CH 11000 – CH 15000

The Project Penswastaan Lebuhraya Bertingkat Sungai Besi – Ulu Kelang (SUKE) (Package CB1) was completed within a 30-month timeframe. This package, spanning from CH:11070 to CH:15000, is subdivided into two sections: Section B7 (CH:11070 to CH:13000) and Section B8 (CH:13000 to CH:15000), totalling nearly 4 kilometres in length.

The direct launching of 40-meter-long beams at a height of 41 meters above ground level is a testament to the engineering techniques and expertise employed in the construction of elevated highways. Cergas Murni project team demonstrated their ability to manage and execute large-scale infrastructure projects within stringent timelines.

Contract Value: RM 550,099,330.00

Project Start Date: 29th August 2016

Completion Date: 28th February 2022

Our Client: Turnpike Synergy Sdn Bhd